
Handrails fitted before the lift
Bridge deck installation moves panel by panel. Panelised bridge deck work leaves little room for slow handrail setup.
Each Transfloor panel had to be placed on a steel girder bridge structure. Once the first panel was down, the next panels had to follow side by side. That sequence created a clear access issue. The crew needed edge protection in place before workers were exposed at height.
The better method was to dress each panel with handrails on the ground before the crane lift. If edge protection is fitted after each panel lands, crews spend more time working at height before the area is protected. That adds labour and slows the work front.
A ground-fitted system changes the task. The panel arrives with handrails already in place, so the protection moves with the install sequence.
For this project, the NONDRILL system connected quickly, suited the Transfloor panel and supported the crane-lift methodology.
Project ContextÂ
This work took place on the Big Build Eastern Freeway – Burke to Tram Alliance project.Â
The scenario occurred during bridge deck works where Transfloor decking panels were installed on the bridge structure.Â
The client and project engineer had worked with SafeSmart before on-site access challenges across major infrastructure works, including the West Gate Tunnel Project.Â
That existing relationship helped the project team move from site issues to a practical handrail method.
The Challenge
The crew needed to install Transfloor decking panels on a steel girder bridge structure.
Before each segment was lifted, the panel needed to be dressed on the ground with a handrail system. This reduced the need to install handrails at height.
The preferred method also had to reduce reliance on a scaffold-based handrail installation. The team needed a system that could be fitted as part of the panel preparation process.
The site constraints were clear:
- Panels had to be crane-lifted into position.
- Handrails had to suit the panel layout.
- The work front changed as panels were placed side by side.
- Workers needed to stay behind handrails during flooring works.
The SolutionÂ
SafeSmart provided the NONDRILL handrail system as a solution.Â
Each Transfloor panel already incorporated lifting anchors for crane handling. The project method added anchor points that the handrail system could attach to.Â
The NONDRILL handrail system connected to a 2.5 cone anchor in the Transfloor panel.
The proposed handrail fitting used a non-scaffold grub screw connection. This enabled on-site labourers to dress the panel with handrails at ground level before the lift.

This changed the work method without compromising project timelines. The panel was prepared on the ground, lifted into position and installed with edge protection already fitted.
Outcomes and Benefits
Less handrail work at heightÂ
The handrails were installed while the Transfloor panel was still on the ground. This reduced handrail installation work after the panel was placed on the bridge structure.Â
Protection moved with the panel sequenceÂ
The quick connection to the cone anchor allowed workers to modify and relocate the handrail across varying Transfloor panels.Â
Workers stayed behind handrailsÂ
The system helped workers stay behind handrails while installing flooring for the EBTA bridge alignment.Â
The install sequence stayed controlledÂ
The handrails were part of the panel preparation process. The crew could focus on placement and flooring works once the panel reached the bridge structure.Â
Documentation supported the site methodÂ
SafeSmart supplied installation guides, uninstallation guides, certificates, third-party engineering lifting certificates and gate design drawings.

AdaptabilityÂ
This method suits more than one bridge deck.
A ground-fitted handrail system can be considered for panelised works where compatible anchors or ferrules are available.
Each use still needs review against the panel design, lift method, site sequence and approved documentation.
The operational gain on timelines and safety was clear to project engineers. Edge protection fitted before the work reached height was a clear better way to work.
Feature Breakdown
Ground-level handrail installationÂ
The handrails were fitted while the Transfloor panel was on the ground. This gave the crew better control before the panel entered the bridge work area.Â
NONDRILL cone-anchor connectionÂ
The system is connected to a 2.5 cone anchor in the Transfloor panel. This gave the handrail a defined connection point without drilling into the panel during site installation.Â

Non-scaffold grub screw fitting
The fitting used a grub screw connection. This supported ground-level panel dressing before the crane lift.
Relocatable handrail layout
The quick connection allowed workers to modify and relocate the handrail as panel layouts changed.
Lift-ready sequence
The dressed panel could be crane lifted into position with handrails already installed. Edge protection became part of the lift sequence.
Project support documentation
SafeSmart supplied install documents, certificates, lifting certificates and gate design drawings to support the method.
The Better Way for Bridge Panel Edge ProtectionÂ
The safer method started before the lift.Â
By fitting NONDRILL handrails to the Transfloor panels at ground level, the crew reduced handrail work at height and kept protection moving with the bridge deck sequence.Â
The panel arrived with handrails already in place. That is the operational point that mattered on site.Â


